Initial commissioning of ion beams at SPIRAL2
Résumé
The official reception of the SPIRAL2 accelerator
building occurred in October 2014. In parallel, the
installation of the accelerator components has started in
June 2013. The first part of the beam commissioning,
including the ECR sources, the LEBTs and the 88 MHz
RFQ should start in December, with an injection in the
Linac by mid-2015. This paper describes the status of the
accelerator components and installation, and the
philosophy retained to commission the light and heavy
ion beams at various required final energies.